Qatargas 3

Qatargas 3 - Economies of scale

The Qatargas 3 (QG3) project involved the construction of a new LNG mega-train (Train 6) with a capacity of 7.8 million tonnes per annum (MTA). Production from Train 6 started in November 2010.
 
The LNG produced by QG3 is transported to market on a fleet of ten ships each with a capacity of approximately 210,000 - 266,000 cubic metres. The upstream platforms and infrastructure consist of three unmanned platforms, 33 wells and two subsea pipelines, all of which are shared with the Qatargas 4 project. Qatargas 3 produces 1.4 billion standard cubic feet of gas per day, delivering LNG and substantial volumes of condensate and LPG.

Qatargas 3 utilises the same Air Products proprietary APX process technology as Qatargas 2. This helps to achieve economies of scale and integration which puts Qatargas ahead of its competitors. The Qatargas 3 and Qatargas 4 projects were developed and executed by a Joint Asset Development Team to capture synergies between the two projects.

QG 3 Train 6 ships its LNG predominantly to the United States, Asia and Europe. At full operational capacity, the train is capable of providing approximately one billion cubic feet of gas per day for 25 years.

Facts and figures about Qatargas 3:

Shareholders

  • Qatar Petroleum 68.5%
  • ConocoPhillips 30%
  • Mitsui & Co. Ltd 1.5%

Train capacity

  • One train with a capacity of 7.8 mtpa

First cargo expected

  • 2010

Key events To Date

  • Heads of Agreement – July 2003
  • FEED contracts awarded – January 2005
  • Financing closed – December 2005
  • Onshore EPC award – December 2005
  • Offshore Jackets F and I Award – December 2005
  • Foundation stone laid – April 2006
  • Offshore Topsides EPC award – June 2006
  • Offshore Pipeline Detailed Engineering Award – June 2006
  • Offshore Installation of two Wellhead Platform Jackets – September and November 2006
  • Rig arrived in the North Field and spudded its first well - May 2007
  • Installation of the first of three wellhead platform topsides - June 2009
  • Installation of the final wellhead platform topside - October 2009

 


Please click here to download a pdf version of the fact sheet.
Please click here to view images.

 

 News

Qatargas Achieves Premier Safety Milestone
Qatargas recently achieved an exceptional safety m...
Qatargas and BOTAŞ (Turkey) Sign New LNG Agreement
Qatargas, the World’s Premier Liquefied Natural Ga...
Separator